2 week look ahead and traffic detour plan for the Phase 1 Sanitary Sewer Job in Highlands.

Mainline crew will be continuing to work between North St and Miller St along Bay Ave in the beginning of the week and then working between Miller and Valley towards the end of the week.

Second Crew will begin the week with setting up the dewatering system along Bay Ave, then work on testing, inlet reconstruction and decommissioning the rest of the week.