2 week look ahead and traffic detour plan for the Phase 1 Sanitary Sewer Job in Highlands.
National Watermain will be back on-site in the beginning of the week to continue the clean and tv of various completed lines throughout the project.
Roman E&G crew will finish the remaining lateral work and then begin miscellaneous restoration and punchlist work.
Right now, Carroccia is scheduled to be on-site the Tuesday after the holiday starting with the concrete work on the local portions of Bay Ave and Waterwitch Ave.