Menu Close

PHASE 1 SANITARY SEWER JOB 2 WEEK LOOK AHEAD AND TRAFFIC DETOUR PLAN

2 week look ahead and traffic detour plan for the Phase 1 Sanitary Sewer Job in Highlands.

Mainline Crew will finish up on the installation of the by-pass system for the Waterwitch Pump Station next week. Followed by Main, Force Main, and Manhole installation from the pump station to Bay Ave along Waterwitch.

Second Crew will continue assisting with the well drilling process on Bay Avenue from North Street to Atlantic over the next couple of weeks.

National Watermain will be on-site starting Monday 3/11 to clean and tv the newly installed sections of sewer main, tentative schedule is as followed:

-Waterwitch (Local)

-North St 

-Bay Ave (North to Jackson)

-Bay Ave (Huddy to Sea Drift)

-Linden Ave

-Waterwitch Ave (County)

Posted in Announcements, Project Updates, Public Notices