Phase 1 Sanitary Sewer Project 2 Week Look Ahead

Roman Crew will be installing the new lateral to ET AL Restaurant at the beginning of this week, and then towards the middle of the week moving to working on trench maintenance on Linden. Roman has coordinated with ET AL Restaurant and Gravelly Point Rd President on the work schedule for next week.

Carroccia concrete crew will be finishing up on Linden on Monday, then moving to Waterwitch and Bay.