Phase 1 Sanitary Sewer Improvements

January 27, 2022: Notice to Bidders Phase 1 Sanitary Sewer Improvements

Update – June 27, 2022

Sanitary Work approximately 7/23 to 11/30

  • Linden 7/27 to 8/23
  • Bay 8/18 to 10/11
  • Central 10/3 to 10/19
  • Ocean 10/12 to 10/27
  • Beach Blvd 10/20 to 10/31
  • Gravelly 10/26 to 11/18
  • Waterwitch P1 11/2 to 11/18
  • William P1 11/17 to 11/18
  • Waterwitch P2 11/21 to 11/29
  • William P2 11/21 to 11/22
  • Ralph 11/23 to 11/29
  • North 11/28 to 11/30
  • South Bay work starting 6/27, substantially complete in August, complete due in September