Sanitary Sewer Work Schedule: 9/18 – 10/1

Mainline crew is scheduled to finish up on Bay Ave. by the middle of next week and then shift over to Linden Ave. and Waterwitch for the remainder of the next 2 weeks.

Bay Ave.: September 18 – 19

Linden Ave.: September 19 – 26

Ralph St.: September 20

Waterwitch: September 26 – 29

Sign up for Nixle to get alerts.