Mainline crew will be finishing up on Waterwitch towards the end of next week, then they will be transitioning to Bay Ave at the intersection of Bay and Washington to install Mainline from that intersection to the intersection of Bay and Waterwitch.
The second crew will be air testing the lines of Central, Ocean and Beach starting the beginning of next week. They will then transition to decommissioning wells on those side streets and then the week of 10/23 they will begin to install more deep wells along Bay Avenue from North St to Valley St.